Mediacom Maintenance 7/8/20
Scheduled Maintenance Report for MOREnet Service
Completed
The scheduled maintenance has been completed.
Posted Jul 16, 2020 - 17:50 CDT
Scheduled
Mediacom technicians will be performing fiber relocation in the Mt Vernon MO area that will cause a service outage on the following circuits.

Circuits Impacted:
Billings R-IV
Brunswick R-II
Carrollton Public Library
Cassville Branch Barry Lawrence Regional Library
Dade County Library
Diamond R-IV
Exeter R-VI
Forsyth R-III
Golden City R-III
Greenfield R-IV
Lincoln University
Mansfield R-IV
McDonald Co R-I
Miller Branch Barry Lawrence Regional Library
Miller R-II
Missouri River Regional Library Main Branch
Norborne R-VIII
Salisbury R-IV
Sarcoxie R-II
South Harrison Co R-II
Strafford R-VI
University Physicians Jefferson City Dermatology
Willard R-II
Posted Jul 02, 2020 - 15:09 CDT
This scheduled maintenance affected: MOREnet Network (Carrier Network).