MOREnet fiber relocation in Sikeston, MO 12/2/22
Scheduled Maintenance Report for MOREnet Service
Completed
The scheduled maintenance has been completed.
Posted Dec 02, 2022 - 05:00 CST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 02, 2022 - 00:00 CST
Scheduled
An underlying carrier will be performing a fiber move due to a MoDOT road construction mandate in the Sikeston area on 12/2/22 beginning at 12:01am CST. This will require cutting and splicing in a new section of cable and will affect the circuit(s) listed below during the maintenance window.

The following members will be impacted by the fiber relocation. All other members should see a traffic switch during the maintenance.

New Madrid R-I
New Madrid Lilbourne Elementary
New Madrid Elementary
New Madrid Matthews Elementary

The following member should see a traffic switch

Risco R-II
Malden R-I
Posted Nov 28, 2022 - 11:31 CST
This scheduled maintenance affected: MOREnet Network (MOREnet Fiber).