Root Cause: A fiber cut in Belle, MO, impacted client services. Fix Action: The fiber was spliced, thus restoring client services to a stable condition.
MOREnet NOC
Posted Nov 20, 2025 - 08:38 CST
Identified
Brightspeed and Lumen NOC's are standing by for confirmation that excavation is underway.
MOREnet NOC
Posted Nov 19, 2025 - 20:21 CST
Update
A secondary LEC fiber Repair Team is en route to the fault site with a two-hour ETA. The next update will be issued upon their arrival.
MOREnet NOC
Posted Nov 19, 2025 - 17:06 CST
Update
A 24-strand cut fiber was identified due third-party construction activity in the Belle, MO vicinity. Splicing crews are on their way.
MOREnet NOC
Posted Nov 19, 2025 - 14:29 CST
Investigating
Fiber has been hit. Both vendors have been engaged for dispatch. Affected sites are:
Maries County Library Belle - Heartland Regional Library System Maries Co. R-II Maries Co. R-II - Middle School
Updates will follow.
MOREnet NOC
Posted Nov 19, 2025 - 13:09 CST